Materials and bill of quantities

Have you received a full and accurate copy of the bill of quantities for this project?

Rehabilitation of a school building — Institut technique Le Progrès ·

Reported during the monitoring visit of 12 January 2026.

Verified

Resolved through Advocacy

Status Verified
0 daysSince the report
MediumSeverity
CategoryMaterials and bill of quantities

History

  1. Fixed

    · Monitor

  2. Verified

    · Monitor

  3. Reported

    · Monitor

  4. Progress

    · Anonymous citizen

    Problem still observed on 13 February 2026.

  5. Proof of fix

    · Anonymous citizen

    Fix observed during the monitoring visit of 14 May 2026.

How the problem was fixed

A copy of the bill of quantities was handed to the Club and posted at the school.

Case study

Bill of quantities not shared: problem resolved at Institut technique Le Progrès thanks to citizen monitoring

The Integrity Club reported on EduCheck: bill of quantities not shared. The problem was published and sent to the project management committee and the contractor.

Read the case study