Accessibility (disability)
Will the completed project be accessible for people with disabilities?
Rehabilitation of a school building — Institut technique Le Progrès ·
Reported during the monitoring visit of 12 January 2026.
Resolved through Advocacy
History
-
Fixed
The plans were changed and a ramp built at the entrance of the building.
-
Reported
-
Proof of fix
Fix observed during the monitoring visit of 13 February 2026.
-
Verified (upcoming step)
How the problem was fixed
The plans were changed and a ramp built at the entrance of the building.
Case study
Building not accessible to people living with disabilities: problem fixed at Institut technique Le Progrès thanks to citizen monitoring
The Integrity Club reported on EduCheck: building not accessible to people living with disabilities. The problem was published and sent to the project management committee and the contractor.