Building sites followed
School construction projects followed by monitors, from building work to handover.
- infrastructures followed
- 32
- open problems
- 81
- resolution rate
- 31 %
6 projects
The map uses more mobile data. The list shows the same information.
- Open problems
- In progress
- All fixed
- No visit yet
Construction projectSud-Kivu
Rainwater harvesting tank — Institut technique Matumaini
- Open
- 5
- Fixed
- 0
- Verified
- 0
Last visit: 31 January 2026
No response
Construction projectSud-Kivu
Drinking water supply — Institut La Réussite
- Open
- 4
- Fixed
- 0
- Verified
- 0
Last visit: 20 November 2025
No response
Construction projectKinshasa
Drinking water supply — École primaire Les Grands Lacs
- Open
- 3
- Fixed
- 0
- Verified
- 0
Last visit: 6 February 2026
No response
Construction projectSud-Kivu
Drinking water supply — Institut La Victoire
- Open
- 2
- Fixed
- 1
- Verified
- 4
Last visit: 29 April 2026
No response
Construction projectKinshasa
Rainwater harvesting tank — Institut technique Saint-Joseph
- Open
- 2
- Fixed
- 0
- Verified
- 0
Last visit: 9 January 2026
No response
Construction projectKinshasa
Rainwater harvesting tank — École primaire Tujenge
- Open
- 2
- Fixed
- 4
- Verified
- 0
Last visit: 31 May 2026
No response